Another miscellaneous day + Fixed video link

Nothing framing was wise done today but we got a lot of other random things done.


Had someone come today to run the copper tubing in the trench for the new 1" water line (on the left).  Inspection is scheduled for Monday.


Cut the window well drain pipe down to grade and installed the grate:


 Did the same thing with the pipe going into the top of the drywell.  This is not a drain, however, just a pop-up emitter in case the drywell ever gets full.


This was the big project.  We got the sewer line run through the wall, sloped properly, then waterproofed around it and then backfilled.  So now all the backfill in the backyard is complete!

Another view of the side showing the backfilled area:

Also, on the inside where the sewer line came in to the house we filled in the large hole that was made in the concrete to get the pipe to fit through.  Hard to tell with the lighting but it is pretty much smoothed out. It will be hidden inside a wall anyways.

Also, this is the corrected video link from yesterday: