Relatively uneventful day progress wise today. Interior demo is nearly complete, excavation has just about 2 hours of work left. They have started building the formwork for the footers...hoping to have footers poured on Wednesday, inspection and weather permitting.
Two large deliveries today: Type II EPS foam insulation board (foundation walls, basement slab perimeter) (pictured) and the Henry Blueskin foundation waterproofing membrane.
Picture #1: Shipment of monoliths arrived from the movie '2010 Space Odyssey'